DuPont Schedule: the 28-Day Rotating Shift Pattern

Four crews, 12-hour shifts, and a full week off every cycle. Generate your crew calendar below — free, no signup.

Tip: choose “Save as PDF” in the print dialog for a high-resolution file.
Day shift Night shift Off

September 2026

DuPont Schedule
SunMonTueWedThuFriSat
1
ADayBOffCOffDNight
2
AOffBNightCDayDOff
3
AOffBNightCDayDOff
4
AOffBNightCDayDOff
5
AOffBNightCOffDDay
6
AOffBOffCNightDDay
7
AOffBOffCNightDDay
8
AOffBOffCNightDDay
9
ANightBDayCOffDOff
10
ANightBDayCOffDOff
11
ANightBDayCOffDOff
12
ANightBOffCDayDOff
13
AOffBNightCDayDOff
14
AOffBNightCDayDOff
15
AOffBNightCDayDOff
16
ADayBOffCOffDNight
17
ADayBOffCOffDNight
18
ADayBOffCOffDNight
19
AOffBDayCOffDNight
20
ANightBDayCOffDOff
21
ANightBDayCOffDOff
22
ANightBDayCOffDOff
23
AOffBOffCNightDDay
24
AOffBOffCNightDDay
25
AOffBOffCNightDDay
26
ADayBOffCNightDOff
27
ADayBOffCOffDNight
28
ADayBOffCOffDNight
29
ADayBOffCOffDNight
30
AOffBNightCDayDOff
Every day: one crew on days, one on nights, two crews off.

What is the DuPont schedule?

The DuPont schedule is a rotating shift pattern built for operations that never stop. It takes its name from the DuPont chemical plants that popularized it in the 1950s, where reactors run around the clock and someone has to be watching them at 3 a.m. on a Sunday. Four crews share the load, working 12-hour shifts on a 28-day cycle, so the plant is covered every hour of every day while each worker averages 42 hours a week.

DuPont schedule: one full 28-day cycle for 4 crews — each crew works 4 nights, 3 off, 3 days, 1 off, 3 nights, 3 off, 4 days, then 7 offCrew ACrew BCrew CCrew DDayNightOff
One full 28-day DuPont schedule cycle, all 4 crews. Each crew runs the same sequence, starting 7 days apart.

How the 28-day cycle works

Every crew follows the same sequence: 4 night shifts → 3 off → 3 day shifts → 1 off → 3 night shifts → 3 off → 4 day shifts → 7 off. The four crews are staggered exactly one week apart, which means coverage never moves: on any given day, one crew is on days, one crew is on nights, and two crews are off. After 28 days the pattern closes on itself and repeats forever.

The arithmetic works out cleanly: 14 shifts per 28 days, 168 hours per cycle, an average of 42 hours per week. Because the Fair Labor Standards Act counts overtime by the workweek rather than by the cycle average, the long weeks in a DuPont cycle can trigger real overtime — worth checking with your payroll team before you adopt it.

The part everyone talks about: the 7-day break

Ask DuPont workers what keeps them on the pattern and you will hear one answer first: the week off. Every 28 days, each crew gets seven consecutive days away — a full vacation-length break thirteen times a year without touching PTO. Veterans describe a second benefit that matters just as much: total predictability. The pattern never changes, so experienced workers can tell you years in advance whether they are working a given birthday or holiday without opening the calendar.

The hard part: the “week from hell”

The same veterans will warn you about the middle of the cycle. The stretch of 3 day shifts, a single day off, then 3 night shifts forces a body clock flip in under 24 hours, and crews consistently call it the roughest week of the rotation. It is the price of the long break, and whether that trade is worth it is genuinely personal — workers with young kids and spouses on standard schedules tend to feel it most, since weekends on shift are built into the pattern.

Who uses it

Chemical and refining plants, paper mills, manufacturers with continuous lines, power stations, and any 24/7 operation that wants deep coverage with built-in recovery time. If your workplace needs two crews resting for every two on duty, the DuPont schedule is the classic answer. Adoption tip from crews that have lived through the switch: publish the calendar at least one full cycle ahead, and decide the overtime rules for the 7-day break before the first cycle starts — the break is the pattern's selling point, and nothing sours it faster than watching it get called in.

Make yours

Scroll up, set the first day of your cycle, and print the calendar — or save it as a PDF and send one to each crew. Comparing patterns? The 2-2-3 schedule trades the long break for shorter weeks and every-other-weekend off, and our rotating shift schedule generator builds both.

DuPont schedule FAQ

Is the DuPont schedule hard to work?

Most of it is manageable, but the middle of the cycle is notorious: 3 day shifts, 1 day off, then 3 night shifts means flipping from days to nights in about 24 hours. Long-tenured workers call it the “week from hell” — and then stay on the pattern anyway, because of what comes next.

What do workers love about the DuPont schedule?

Two things, consistently. The 7-day break every 28 days feels like a free vacation thirteen times a year. And the pattern is completely predictable — it never changes, so workers can plan appointments, trips, and family events months ahead without checking a roster.

Does everyone actually get the full 7 days off?

On paper, yes. In practice, the break is the first thing that gets eaten when a plant is short-staffed and mandates overtime coverage. If you are evaluating a job that runs DuPont, asking how often the 7-day break survives is one of the smartest questions you can ask.

How is DuPont different from the 2-2-3 schedule?

DuPont is a 28-day rotation with a 7-day break and perfect predictability — the same weekdays are always yours. The 2-2-3 schedule is a 14-day rhythm with no single crushing week and a 3-day weekend every other week, but your days off drift through the week. DuPont workers cite predictability as the reason they would not switch; 2-2-3 workers cite the short weeks.

Who uses the DuPont schedule?

Continuous operations: chemical plants (where it originated at DuPont), oil refineries, paper and steel mills, power generation, and manufacturing lines that run 24/7. It fits anywhere that needs exactly one day crew and one night crew on duty at all times.

Is there a “reverse DuPont”?

Yes — some plants run the same 28-day structure but open the cycle with 4 day shifts and close it with nights instead of the reverse. The generator above handles both: just pick the start date that lands your crew on the right phase of the pattern.